DONE - Fairlands Elementary School - Site Fencing Project
DSA Approved: November 28, 2018
Board Approved Construction Agreement: February 26, 2019
Construction Started: April 2019
Estimated Completion: August 2019
Key:
Red = Fence to be removed
Blue = Fence to remain
Green = New Fence
Work in progress over Spring Break