Facilities & Construction » Amador Valley High School - Portable Replacement and New Science Labs Project

Amador Valley High School - Portable Replacement and New Science Labs Project

Status
February 1, 2022 - Things are wrapping up and soon students and staff will be able to occupy the new 2 story building!  Technology items have been delivered and installed and new furniture for all the classrooms is being delivered this week.
Status
As of November 2021, the majority of the building work has gone into the interior.  The steel roofing is completed and everyday has a multitude of various trades onsite, with casework being the latest addition.  Aesthetically, the building moves closer towards completion as painters bring color in on the outside. 
Status
 
May 7, 2021
Going vertical!  Site work and building pads have been completed the construction team is now framing the building.  The building pad and utilities were a challenge due to several unforeseen conditions but with framing in the building work is starting to accelerate.  
January 13, 2021
Construction began in late October.  Currently the building pad is constructed, site utilities have been relocated and the footings are beginning to be dug.  
 
September 12, 2020
DSA Approved!  The project has hit a major milestone, DSA has approved the project drawings for construction.  The project has now entered the bidding phase.  Bids from contractors are due September 22, 2020.  Ground breaking will take place the first week in October.  Check back for the ground breaking ceremony date we would love to see you there.
 
May 21, 2020
The project plans to DSA in late 2019 and are anticipating the drawings to be returned and approved by the start of summer. In the interim, the design team along with the district construction managers are doing thorough page by page constructability reviews of the drawings and technical specifications. Through these detailed examinations, the team will be able to discover and root out potential issues that could occur during the bidding and/or construction phase.
_____________________________________________________________________________________________________________________
 
Schedule:
The AVHS project is expected to go out for bid in summer of 2020 with construction starting in fall. The anticipated completion fall 2021.

Scope:
Construction of a new 2-story classroom building and associated site work in 2 phases.
Phase 1: Construction of 2 SDC classrooms, 2 science classrooms with prep rooms, 1 standard classroom, custodian room, utility rooms, elevator, restrooms and related site work.
Phase 2: Construction of 6 standard classrooms, 1 science classroom with prep room, and related site work.

Budget: 
$16,684,000 (Project Budget)