Facilities & Construction » District Wide HVAC & Roof Upgrades

District Wide HVAC & Roof Upgrades

Status
 
December 2021
The HVAC and Roofing Project was a major challenge as there is only a narrow window (Summer) where we can do this work and not be disruptive to teachers, staff, and students. For this past summer, this improvement project took place at several campuses; Valley View, Alisal, Pleasanton Middle, Harvest Park, and Amador.  Alongside replacing the HVAC units, there was significant roofing work done, with the installation of single ply roofing  for several buildings at Harvest Park, Pleasanton Middle, and Valley View and replacing several aging roofs at Amador with a new built-up system.

Status

January 13, 2021

Bidding for packages 3 and 4 has been completed.  The low bidder was Bobo Construction Inc..  They have begun the procurement process and will be completing these projects by the end of Summer 2021.

 

November 10, 2020 

Packages 3-5 are now out to bid.  Bid's will be received for these packages the week of November 16th.  These projects include Alisal Elementary School, Amador Valley High School, Fairlands Elementary School, Harvest Park Middle School, Pleasanton Middle School, Valley View Elementary School.

 

September 12, 2020

Packages 1 and 2 are now complete!  This included work at Harvest Park, PMS, Alisal and Fairlands.

_____________________________________________________________________________________________________________________

 

Schedule:

District wide roofing and HVAC projects will be ongoing over the next three years.  A priority has been set based on the roof and HVAC units remaining lifespan. 


Scope:

Replace and repair existing roofing, HVAC and any water damage discovered.  


Budget: 

$62,814,653.00 (Project Budget)