Foothill High School: Portable Replacement and New Science Labs

Project Information

Schedule

The project is expected to go out for bid in summer of 2020 with construction starting in the summer. The anticipated construction completion is fall 2021.

Scope

Construction of a new 2-story classroom building and associated site work.

Phase 1: Construction of three engineering classrooms, two science classrooms with utility rooms, elevator and related site work. Provide automatic fire sprinkler system at existing Building J.

Phase 2: Construction of one engineering classroom, one science prep room, two computer labs, restroom, custodial room and related site work.

Budget

$12,028,000

Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS
Portable Replacement & New Classroom Building – Foothill HS

Project Status Updates